Permits and approvals

Short answer

A Santorini project may need several approvals running in parallel: the building permit itself, archaeological clearance where there is excavation, Council of Architecture review in designated settlements, and cadastral clarity before any of them. The order matters more than the paperwork.

The approvals, and what triggers each

What your project probably needs
ApprovalTriggered byWhere it sits
Topographic surveyAlmost any applicationFirst — everything else builds on it
Κτηματολόγιο checkAny application, and any purchaseFirst — a discrepancy here blocks everything
Architectural designAny permitted workEarly, and constrained by settlement rules
Structural engineeringAny structural workWith the design, not after it
Archaeological approvalExcavationBefore the design is frozen
Council of ArchitectureDesignated settlementsBefore the permit
Building permitStructural, external or new workThe main event
LegalisationExisting unauthorised workBefore any new application
ΠΕΑ energy certificateSale, long lease, some worksAt completion or at sale
Short-term rental complianceListing a propertyBefore listing
Tourist accommodation licenceOperating as accommodationBefore operating

Why the order is the whole game

Approvals are not a set of forms to submit in parallel. Several of them constrain the design, and a design produced before those constraints are known is a design that gets produced twice.

  1. Cadastral and title first. A Κτηματολόγιο discrepancy or an unauthorised earlier addition will stop a permit application. Found at the start it is a task; found at submission it is months.
  2. Settlement designation next. If the property is in a designated settlement, the external appearance rules define the envelope before anyone draws an elevation.
  3. Archaeology before the foundation design. If the Ephorate requires investigation and finds something, the foundation design changes. Designing first means designing again.
  4. Then design, engineering and the permit file.

Who does what

These roles are set by Greek practice. You appoint the professionals directly; a contractor coordinates them and builds to what they produce.

Architect (αρχιτέκτονας μηχανικός)
The scheme, the elevations, and the case for approval in a designated settlement.
Civil engineer (πολιτικός μηχανικός)
Structural design and calculations, including seismic. Signs the structural file.
Supervising engineer (επιβλέπων μηχανικός)
Statutory supervision that the work follows the approved design.
Surveyor (τοπογράφος)
The topographic survey that underpins the application.
Contractor
Building it as designed, and coordinating the sequence between everyone above.

More detail in who does what on a Greek build.

Questions people actually ask

Do I need a permit for internal work?

It depends what you touch. Purely internal, non-structural work with no change to openings frequently sits outside a full permit; anything structural, any new opening, and anything externally visible in a designated settlement does not. We tell you which side you are on before you commit.

Can you handle the whole approval process for me?

It gets coordinated, and the professionals are appointed by you directly so their responsibility to you is unambiguous. If you do not have an architect or engineer we will suggest people we have worked with.

How long does the whole thing take?

Months rather than weeks on almost any permitted project, and longer where archaeology or a designated settlement is involved. See the permit timeline tool for a sequenced view by property type.

What happens if I build without a permit?

You create an αυθαίρετο on your title. It surfaces at sale, at licensing and at insurance, and legalising it afterwards is more expensive and sometimes impossible. See legalisation.

One request. The right trade.

Tell us what needs doing

One request, two minutes. We read every one and point you at the tradesperson who handles this. Free, and you deal with them directly.

Message us

Ask about this page

A question about this specific job, or about something else entirely. It reaches a person, not a queue, and there is no obligation.

Your message will tell us you were reading Permits and approvals

Plain words are better than trade words. If you have photographs, say so and reply to our email with them attached.

We use what you send only to answer you. Privacy.