Permit timeline visualiser

The order matters more than the paperwork. This shows you the order.

Short answer

This tool sequences the approvals a Santorini project needs based on property type, whether it is in a designated settlement, whether excavation is involved and whether there is earlier unauthorised work — with indicative elapsed durations and the governing constraint named at each step.

What is the project?
Which of these apply?

Your approval sequence

  1. Title and cadastral checkDays to many months

    Confirm ownership is clean and that what is recorded matches what is built. Unfinished inheritance and undivided shares among heirs are the most common cause of a long delay here.

  2. Topographic survey1–3 weeks

    A registered surveyor establishes boundaries, levels and the plot's relationship to everything around it. Every subsequent drawing is built on this.

  3. Legalisation of earlier unauthorised workMonths

    If a previous owner built without permission — an extension, an enclosed terrace, a converted store — it must be regularised before a new application proceeds. Extremely common on older property.

  4. Settlement designation checkDays

    Establish whether the property is in a designated traditional settlement and what the external appearance controls are. This defines the design envelope before anything is drawn.

  5. Architectural design4–12 weeks

    The scheme is developed within the planning envelope and the settlement controls. Client decision speed is usually the governing variable.

  6. Archaeological approval — Ephorate of AntiquitiesWeeks to many months

    Engaged wherever there is excavation. Can require a watching brief, a trial trench or a fuller assessment, and what is found can change the foundation design. This is why it precedes structural design.

  7. Council of Architecture reviewWeeks to months

    In designated settlements the external design is reviewed before the permit. A scheme not tested against the controls is the one that gets sent back.

  8. Structural design3–8 weeks

    A civil engineer designs the structure to the Greek seismic requirements and signs the structural file, carrying statutory responsibility for it.

  9. Permit file assembly and submission2–6 weeks

    Drawings, calculations, surveys, prior approvals and statutory documentation submitted together. An incomplete file is the most avoidable delay in the whole sequence.

  10. Permit issued; supervising engineer appointedVariable

    Only at this point is the construction programme real. A supervising engineer is appointed and their inspection points are programmed into the works.

Indicative only. These are ranges from ordinary practice offered so you can plan, not statutory service standards. Your project will differ, and the realistic view of your own file comes after your engineer has seen it. See how long a permit really takes.

Why the order is the whole game

Approvals are not a set of forms to submit in parallel. Several of them constrain the design, and a design produced before those constraints are known is a design that gets produced twice.

The steps marked in the sequence above are the ones that most often blow a programme, and all four are discoverable before you spend anything on design:

  • Title and cadastral position. An unresolved inheritance or a registered area that does not match the plot. See Ktimatologio.
  • Earlier unauthorised work. It must be regularised before a new application proceeds. See legalisation.
  • Archaeological requirements. What the Ephorate requires, and finds, can change the foundation design. See archaeological approval.
  • Settlement review. A scheme not tested against the external controls is the one sent back. See Council of Architecture.

Checking all four costs a few weeks at the start. Discovering any of them after the design is engineered costs months.

What you can do while you wait

Using the approval period well is what separates a well-run project from a stalled one.

  • Ground investigation and trial pits — the structural design needs them anyway. See foundations in volcanic ground.
  • Detailed survey and opening up, on a property you already own.
  • Finish selection and long-lead identification, so ordering can happen the day the permit issues.
  • Contractor selection and pricing, so the programme is ready to start rather than starting to be planned.

What you cannot do is start permitted work. Doing so creates an unauthorised structure on your own title, which is the exact problem this page exists to help you avoid.

One request. The right trade.

Tell us what needs doing

One request, two minutes. We read every one and point you at the tradesperson who handles this. Free, and you deal with them directly.