Why the order is the whole game
Approvals are not a set of forms to submit in parallel. Several of them constrain the design, and a design produced before those constraints are known is a design that gets produced twice.
The steps marked in the sequence above are the ones that most often blow a programme, and all four are discoverable before you spend anything on design:
- Title and cadastral position. An unresolved inheritance or a registered area that does not match the plot. See Ktimatologio.
- Earlier unauthorised work. It must be regularised before a new application proceeds. See legalisation.
- Archaeological requirements. What the Ephorate requires, and finds, can change the foundation design. See archaeological approval.
- Settlement review. A scheme not tested against the external controls is the one sent back. See Council of Architecture.
Checking all four costs a few weeks at the start. Discovering any of them after the design is engineered costs months.
What you can do while you wait
Using the approval period well is what separates a well-run project from a stalled one.
- Ground investigation and trial pits — the structural design needs them anyway. See foundations in volcanic ground.
- Detailed survey and opening up, on a property you already own.
- Finish selection and long-lead identification, so ordering can happen the day the permit issues.
- Contractor selection and pricing, so the programme is ready to start rather than starting to be planned.
What you cannot do is start permitted work. Doing so creates an unauthorised structure on your own title, which is the exact problem this page exists to help you avoid.