What to expect
| Typical duration | Closed-season refurbishment Nov–Mar · new build 14–24 months |
|---|---|
| Cost band | Figures live in the cost index |
| Permit required | Yes for structural, external or licensing-relevant work |
| Seasonal constraint | The defining constraint — work is compressed into the closed season |
The closed season is shorter than it looks
On paper you have November to March. In practice the usable window is smaller at both ends: the property has to be emptied, surveyed and stripped before anything starts, and it has to be cleaned, commissioned, snagged and dressed before it opens. The actual construction window in a five-month closed season is frequently under four.
That compression is why hotel work is a different discipline from private work. On a villa a three-week slip is an irritation. On a hotel it is a delayed opening, cancelled bookings and a commercial loss far larger than the value of the works.
| Working back from opening | Stage | Why it sits here |
|---|---|---|
| Opening | Live | — |
| −2 weeks | Dressing, deep clean, final snag | Housekeeping and F&B need the building before guests do |
| −4 weeks | Commissioning and testing | Water, drainage, air conditioning, pool, fire systems |
| −6 weeks | Finishes complete | Last wet trades off site, floors protected |
| −12 weeks | Second fix | Depends entirely on long-lead items having landed |
| −16 weeks | First fix and structure complete | The last point at which a design change is cheap |
| −20 weeks | Strip out and survey complete | What is actually behind the walls is now known |
| −30 weeks | Long-lead items ordered | Before the design is fully finished — this is the decision that saves the programme |
Indicative for a mid-size refurbishment. Yours will differ; the ordering logic will not.
Ordering before the design is finished
This is the single most useful thing we can tell a hotel owner. The programme is not usually lost on site — it is lost waiting for sanitaryware, glazing, joinery or a specific tile that had a ten-week lead time and then missed a sailing.
So we identify the long-lead items in the first month and order them against a frozen sub-set of the design, while the rest of the specification is still moving. It requires committing to some decisions earlier than feels comfortable. It is also the difference between opening on the announced date and not.
Working next to rooms that are occupied
Phased refurbishment — half the hotel trading while the other half is a site — is possible and is often the only commercially viable option. It changes the method substantially.
- Noise-generating work is confined to agreed hours and, in practice, to periods when adjacent rooms are not sold. That has to be agreed with the operator before it is priced, not after.
- Dust and route separation matter more than the work itself. Guests will forgive scaffolding; they will not forgive dust in a room or a corridor they cannot use.
- Material movement has to be scheduled around guest movement, which on a caldera-side hotel with a single stepped access route is genuinely the hardest logistical problem on the job.
- Deliveries and waste removal frequently move to early morning, which affects both cost and the crew you can staff it with.
What refurbishment usually turns out to be
The brief is normally "refresh the rooms". What the strip-out finds is normally one of four things, and none of them is decoration.
- Waterproofing. Terraces and wet rooms above occupied space, detailed years ago without movement joints or a separating layer. This is the most common finding and the most expensive to defer.
- Drainage capacity. A property extended twice on a drainage system sized for the original. Peak occupancy is when it announces itself.
- Electrical loading. Air conditioning, induction, EV charging and pool plant added incrementally onto a distribution board that was adequate in 2004.
- Corrosion at balustrades and fixings. Salt-air degradation of anchors and hardware. Cosmetic-looking, structurally not.
We survey for all four before pricing, because a refurbishment that discovers them in January cannot absorb them.
Licensing and compliance
Physical works on a tourist accommodation property interact with its licensing. Changing room counts, altering fire escape routes, adding a pool or converting space to food and beverage all have consequences beyond the building permit.
A good contractor coordinates with your licensing consultant rather than replacing them, and makes sure the as-built matches what the licence assumes — which is precisely where properties that have been extended informally over the years get caught. See tourist accommodation licensing and legalisation of unauthorised structures.
Questions people actually ask
Can an opening date be guaranteed?
A contractor can commit to a programme, a float allowance and weekly written reporting against it, and we will tell you the moment a date is at risk rather than at the end. Anyone guaranteeing an opening date irrespective of ferry cancellations and supplier lead times is guaranteeing something outside their control.
What is the latest we can start for an April opening?
For a room refurbishment with no structural work and no long-lead items, November is workable. If anything needs manufacturing — joinery, glazing, specific sanitaryware — the ordering decision needs to be made in September, whatever the site start date is.
Do you work with our existing designer?
Usually, yes. Most hotel clients have an interior designer already and a relationship with a specific look. Our role is to make the design buildable inside the window and to flag early where a specification will not land in time.
Can you do a phased refurbishment while we stay open?
Yes, with the noise, dust, access and delivery constraints agreed with the operator before pricing. Phased work costs more per room for the same specification, and it should — the constraint is real.
Who handles the pool between seasons?
Yes — either as part of the works or as a standalone. Closed-season pool care is not optional here: an untreated pool through winter costs far more to recover in March than it does to maintain. See pool maintenance.